Dream Las Vegas Receives Third Extension of Time

Dream Las Vegas Rendering
Credit: DLR Group

The Clark County Zoning Commission approved Shopoff Realty Investments’ third request for an Extension of Time for its stalled Dream Las Vegas resort toward the southern end of the Strip.

The hotel-casino was initially proposed by Shopoff Realty Investments and Contour. DLR Group is the architect. McCarthy Building Companies is the general contractor and current property owner. (NVBEX, Nov. 5)

The 4.7-acre property was signed over to McCarthy Building Companies for lack of payment after construction began. The initial proposal consisted of a 20-story casino with 527 rooms.

County staff argued the project should be considered abandoned due to its extended pause. Commissioners voted against staff’s recommendation. Commissioners said, however, that subsequent extensions are unlikely.

The development team has an additional two years to work on the project, otherwise the permits will expire again.

We thought you may also like these articles...
Boulder City Acts Against Federal Approval of Townsite Solar II
Desert Pines Golf Club Closes to Make Way for Affordable Housing Redevelopment
North Las Vegas Releases Two RFIs for Tule Springs East
ROAD to Housing Act Becomes Law by Default
Brightline West Remains Far from Funding Goal

Leave a Reply

Your email address will not be published. Required fields are marked *

Learn More About Our Services

Mark Hobaica

Mark Hobaica

Executive Vice President

Core Construction

Since 2019, as CORE Construction’s Executive Vice President for Nevada, Mark ensures every client CORE serves receives the highest level of personalized care for every project. Mark’s passion is client Trust. He cares deeply about CORE’s reputation, partnerships and providing the highest quality and services, as well as most honest and best value possible. He has worked in the Las Vegas Valley and for the Public Works sector for nearly 35 years. He began as an owner in a local architectural firm designing and overseeing projects for Public Works clients for nearly 12 years. He clearly understands the expectations of the public sector, as he then directed numerous projects for over 16 years as the City Architect for the City of Henderson. His focus has always been delivering projects using CMAR or Construction Manager at Risk as he has implemented dozens of projects with his trusted approach, while always involving every stakeholder to ensure each individual receives the highest level of services expected.