Brightline West Price Increases by $9B

Rendering of Nevada rail line. Credit: Brightline West
Rendering of Nevada rail line. Credit: Brightline West

The cost of the Brightline West High-Speed Rail project has risen from $12B to nearly $21.1B.

Brightline West recently applied for a $6B federal loan on Sept. 26. The documents submitted alongside the application listed the increased development cost. A spokesperson from Brightline West confirmed the new cost with the Las Vegas Review-Journal.

The project consists of a 218-mile high-speed rail line between Las Vegas and Rancho Cucamonga, Calif. There will be additional stations in Hesperia and Apple Valley Calif. The Rancho Cucamonga station will, if constructed, feature a Metrolink connection to downtown Los Angeles.

Site grading has begun on the Brightline West station. Sewer lines and a box culvert are to be relocated prior to construction of the station. Geotechnical work has also occurred along I-15 throughout both states.

Project Details

All Nevada portions of the project are a collaborative effort between Brightline West and the Nevada Department of Transportation.

The Las Vegas Brightline Station is to be located on a 110.7-acre site in Enterprise. It is being designed by Grimshaw Architects and will be constructed by McCarthy Building Companies. Kaempfer Crowell is providing legal representation. (NVBEX, Jan. 24; June 12)

-image
Maintenance facility in Sloan. Credit: Brightline West

Only 34 miles of the line will be located in Nevada. This section is being designed by Atlas Technical Consultants and is being constructed by Las Vegas Paving Corp.

Additionally, Brightline is planning the Brightline West Maintenance Facility in Sloan. The facility is to total 200KSF. It is being designed by HNTB. The Whiting-Turner Contracting Company is the general contractor.

Developers recently requested an extension of time until July 2, 2029.

We thought you may also like these articles...
Las Vegas Q2 Construction Cost Percent Change Mirrors National Average
Clark County Next to Consider Data Center Restrictions
Phillips 66 and Kinder Morgan Advancing Western Gateway Pipeline
Hard Rock Adding 179KSF Theater to Guitar-Shaped Hotel
Las Vegas Approves 22KSF Westside Apartment Complex

Leave a Reply

Your email address will not be published. Required fields are marked *

Learn More About Our Services

Mark Hobaica

Mark Hobaica

Executive Vice President

Core Construction

Since 2019, as CORE Construction’s Executive Vice President for Nevada, Mark ensures every client CORE serves receives the highest level of personalized care for every project. Mark’s passion is client Trust. He cares deeply about CORE’s reputation, partnerships and providing the highest quality and services, as well as most honest and best value possible. He has worked in the Las Vegas Valley and for the Public Works sector for nearly 35 years. He began as an owner in a local architectural firm designing and overseeing projects for Public Works clients for nearly 12 years. He clearly understands the expectations of the public sector, as he then directed numerous projects for over 16 years as the City Architect for the City of Henderson. His focus has always been delivering projects using CMAR or Construction Manager at Risk as he has implemented dozens of projects with his trusted approach, while always involving every stakeholder to ensure each individual receives the highest level of services expected.