Serving the A/E/C Industry

Latest Stories in Planning & Development...

Monument Hills Master Plan
Las Vegas Approves Purchase Agreement for 6,000-Home Masterplan in Northwestern Las
PD-Halo-Tower-Elevation
Moonwater Capital Continues to Plan 210KSF Halo Tower in Spring Valley
Symphony Park MOF Rendering
Prospect Street Proposes 103.2KSF Medical Facility in Symphony Park
Nevada State University
Nevada State University Planning Expansion with Two Satellite Campuses in the Las Vegas Valley
Revival Aerial Rendering
Madison Capital Group and Ahlquist File Permits for Reno Revival

Latest Stories in Local News...

Carson City Master Plan Listening Sessions Poster
Carson City Holding Listening Session to Discuss Master Plan
FILE PHOTO: The logo of Amazon is seen at the company logistics center in Boves, France, August 8, 2018.
Amazon Planning Delivery Station in Rural Northern Nevada
LOC-SN-Supplemental-Airport
More Details Revealed as Southern Nevada Supplemental Airport Plans Public Meetings
LOC-Royal-Resort-Demo
Liquidation Sale Active for Hotel with Planned August Demolition
TRN-LOC-Unemployment-Rate
Nevada Unemployment Remains High in June

Latest Stories in Trends...

National Association of Home Builders Logo
Multifamily Developer Confidence Up in Q2
July Construction Employment Growth Graph
Construction Employment Growth Weak in July
TRN June 25 Nonres Spending
Nonresidential Construction Spending Down 0.1% in June
TRN-LOC-Unemployment-Rate
Nevada Unemployment Remains High in June
LOC-TRN-June-Employment-Report-Graph-1-
Construction Employment Resumes 2025 Decline in June

Latest Stories in Nevada Projects...

WIP-Ellis-Island
Nevada Projects 08-15-25
Nevada Projects Featured Image of Four Queens Hotel and Casino
Nevada Projects 08-08-25
WIP Album
Nevada Projects 08-01-25
WIP-Hard-Rock
Nevada Projects 07-25-25
WIP-CCSD
Nevada Projects 07-18-25

Latest Stories in Federal...

Solar Panels on a Roof
Environmental Protection Agency Pulls $156M in Nevada-Based Solar Funding
FED-LEG-New-Housing
Proposed Legislation Aims to Increase Housing Supply
FED-LEG-LIHTC-Permanent
Tax Bill Would Make LIHTC Permanent
LOC-FED
New Law to Give N. Las Vegas Authority Over Industrial Park
National_Association_of_Home_Builders_logo
NAHB Praises Supreme Court Environmental Review Decision

Latest Stories in Budget...

LOC-BUD-Vegas-Delaying-CIP-Projs
City of Las Vegas Delaying $19.7M Worth of Capital Improvement Projects
LOC-BUD
Budget Provision Calls for Selling Millions of Acres of Western Federal Land
5e4814b9-051625_nvleg_00368
Proposed AB587 Could Pull $350M from Rainy Day Fund
Tariffs
Southern Nevada Water Authority Discusses Budget and Tariffs
NDOT_logo_t670
NDOT Discusses Budget at NAIOP Southern Nevada Breakfast Panel

Latest Stories in People on the Move...

PPL Palisade Engineering
Industry Professionals 08-12-25
Industrial Professionals
Industry Professionals 08-05-25
PPL-Contractor-of-the-Year-Awards
Industry Professionals 07-29-25
PPL-Mead-Law-Group
Industry Professionals 07-22-25
PPL-Shop-Class
Industry Professionals 07-15-25

Latest Stories in Commercial Real Estate...

CRE-Paradise-Esplanade
Commercial Real Estate 08-12-25
CRE Reverb at Spring Valley
Commercial Real Estate 08-05-25
CRE-LEV
Commercial Real Estate 07-29-2025
CRE-Lev-Apartments
Commercial Real Estate 07-22-25
CRE-2942-Lincoln-Road
Commercial Real Estate 07-15-25

Latest Stories in Legal...

FED-LEG-New-Housing
Proposed Legislation Aims to Increase Housing Supply
FED-LEG-LIHTC-Permanent
Tax Bill Would Make LIHTC Permanent
Byrd-Rule
Public Lands Sale Proposal Removed from Budget Again
LEG-PD-Campus-for-Hope
Lawsuit Filed to Prevent Planned Campus for Hope Transitive Housing Development in Las Vegas
LEG-LOC-AB224
New Law Approves Funding for Rural School District Projects

Latest Stories in Water...

Water-Negotiators
Water Negotiators Duck Meeting to Discuss New Colorado River Plan
LEG-WAT-Help-Hoover-Dam-Act
Proposed Legislation Could Fund Hoover Dam Upgrades
Water
Controversial Water Bill Presented to Assembly Committee
WAT-NV-Water-Efficiency-
Nevada Ranked Most Efficient Water Consumer of Basin States
WAT
EPA Freezes Funding for Walker River Paiute Tribe Water Infrastructure

Maryland Parkway Bus Rapid Transit System Under Construction with $378M Budget

Credit: Regional Transportation Commission of Southern Nevada

By CJ Jorgensen for NEVBEX

The Regional Transportation Commission of Southern Nevada is currently working on the 12.5-mile Let’s Go Maryland Parkway project.

The project is comprised of adding medians to the roads, delegating lanes for buses/bikes and painting those lanes red, sidewalk extensions, 42 new transit shelters, 15 new hydrogen fuel buses and additional shade spots along the route.

The bus rapid transit system is divided into two segments, one in Las Vegas and the other in Clark County. Construction on the Las Vegas portion of the project began on Aug. 5, while construction on the Clark County portion began on Sept. 23.

This marks the fifth bus rapid transit system that RTC has worked on.

The route extends from the South Strip Transit Terminal in the south, all the way up to the LV Medical District in the north, totaling 23 connections along the way. The route will connect Harry Reid International Airport, Boulevard Mall, the University of Nevada Las Vegas’s main and medical campuses, and Sunrise Hospital.

The project began with a CMAR procurement, but ultimately switched over to a low-bid procurement. Due to the system going through two separate jurisdictions, RTC had to put out a bid for each jurisdiction.

Two separate teams from Las Vegas Paving won the bids; Las Vegas Paving is the general contractor for both portions of the project. The design firm for the project is GCW Engineering. Completion is anticipated for September 30, 2026.

Funding & Costs

Maryland Parkway is one of the largest transit routes in the RTC and has been in the making for more than a decade. The current budget gives the project a ceiling of $378M. Brij Gulati, Director of Capital Projects at RTC, is optimistic that the project will end up costing less than the ceiling.

Earlier this year, the U.S. Department of Transportationprovided the RTC with $149.8M in funding for the project.

Construction costs are approximately $225M. An additional 10% will be set aside for the owner contingency. Right-of-way purchases and the 15 buses are also key players in the overall cost. The real estate acquisition company, AtkinsRéalis, assists RTC in approaching owners for right-of-way purchases.

The 15 buses cost $30M and annual operating costs are projected to be approximately $4M.

Future of Maryland Parkway with New BRT System

Gulati stated that BRT systems are more flexible than fixed-transit systems, such as trains and light rail systems.

The BRT will also bring benefits to residents and local businesses. The project will provide more shaded areas around streets, an increase in pedestrian safety and efficient/alternative methods of transportation for locals and visitors alike.

The project is expected to create 1,100 local jobs and contains $33M in local/small business contracts with subcontractors.

Construction Progress: Challenges and Successes

The corridor is home to approximately 63,000 people, 109,000 jobs, 35,000 vehicles and 9,000 transit riders daily. The Let’s Go Maryland Parkway Website has a weekly-updated tracker to display what work is happening on respective sections of the corridor.

Coordination is one of the biggest challenges RTC has faced. As the bus route enters multiple jurisdictions, RTC must communicate effectively with utility companies, the City of Las Vegas and Clark County.

Gulati stated communication was one of the most important aspects of the project. RTC holds weekly meetings with utility companies, as well as representatives from Las Vegas and Clark County. The project comes with a five-year no-cut agreement, meaning the roads cannot go through traffic-impacting construction for five years.

Gulati stated weekly meetings are held with the companies and municipalities and made it a point to express appreciation for the work the companies and municipalities have put into communication. The construction team meets weekly to discuss updates, coordination efforts, budget and schedule.

Bi-weekly meetings are held virtually with stakeholders in the corridor to provide construction updates. This gives stakeholders an opportunity to coordinate events with ongoing construction activities.