Since 2019, as CORE Construction’s Executive Vice President for Nevada, Mark ensures every client CORE serves receives the highest level of personalized care for every project. Mark’s passion is client Trust. He cares deeply about CORE’s reputation, partnerships and providing the highest quality and services, as well as most honest and best value possible. He has worked in the Las Vegas Valley and for the Public Works sector for nearly 35 years. He began as an owner in a local architectural firm designing and overseeing projects for Public Works clients for nearly 12 years. He clearly understands the expectations of the public sector, as he then directed numerous projects for over 16 years as the City Architect for the City of Henderson. His focus has always been delivering projects using CMAR or Construction Manager at Risk as he has implemented dozens of projects with his trusted approach, while always involving every stakeholder to ensure each individual receives the highest level of services expected.
Boulder City Acts Against Federal Approval of Townsite Solar II
NVBEX Staff
The Boulder City City Council has written an appeal letter after unanimously voting to act against the Townsite Solar II data center proposed on nearby federally owned land.
Townsite Solar II was initially proposed by Skyler Capital Management on an 88.5-acre site within Boulder City limits. After the Planning Commission recommended denial of the development, the developer withdrew the application and resubmitted it on federal land.
The Bureau of Land Management then granted its initial approval of the project without allowing public input, which is typically required per the National Environmental Policy Act. NVBEX has extensively covered this project.
Skylar Capital Management previously received approval to build a solar farm and then amended its permit to change the land use for a data center. BLM officials decided the environmental review that had already been conducted for the solar farm was sufficient for the data center.
The pivot to federal land means that any direct economic activity generated from the data center will not benefit Boulder City residents. (Source: Las Vegas Review-Journal)
We thought you may also like these articles...
North Las Vegas Releases Two RFIs for Tule Springs East
Zilberberg International Proposing 71-Unit Apartment Complex in Downtown Las Vegas
Las Vegas Q2 Construction Cost Percent Change Mirrors National Average
M.J. Dean Construction Proposing Hockey Arena in Spring Valley
Hard Rock Adding 179KSF Theater to Guitar-Shaped Hotel
Las Vegas Approves 22KSF Westside Apartment Complex
DC Petersen Receives Approval of 50KSF Warehouse in Sunrise Manor
Nevada Construction Employment Holds Steady in May 2026
Las Vegas Architects Discuss Upcoming Projects and AI Impact in Design
Century Communities Revising Arroyo Townhomes in Spring Valley
DC Petersen Proposing 58.1KSF Warehouse in Spring Valley
Kavison Homes Seeking Extension of Time for Pecos Commons Apartments
Related Articles
Lyon County Presses Ahead with Power Improvement District
Townsite Solar 2 Pivoting to Federal Land, Receives BLM Approval
Clark County Next to Consider Data Center Restrictions
Churchill County Next to Consider Data Center Restrictions
Henderson City Council to Consider Data Center Moratorium
Trending Now
Ken’s Foods Planning 421.3KSF Processing Center Expansion in Clark County
Desert Pines Golf Club Closes to Make Way for Affordable Housing Redevelopment
Nevada Construction Employment Proceeds with 2026 Rebound
Boys & Girls Clubs of Mason Valley Planning New Campus in Silver Springs
Northern Nevada Industrial Market Continues to Chew Away at Recent Deliveries