Since 2019, as CORE Construction’s Executive Vice President for Nevada, Mark ensures every client CORE serves receives the highest level of personalized care for every project. Mark’s passion is client Trust. He cares deeply about CORE’s reputation, partnerships and providing the highest quality and services, as well as most honest and best value possible. He has worked in the Las Vegas Valley and for the Public Works sector for nearly 35 years. He began as an owner in a local architectural firm designing and overseeing projects for Public Works clients for nearly 12 years. He clearly understands the expectations of the public sector, as he then directed numerous projects for over 16 years as the City Architect for the City of Henderson. His focus has always been delivering projects using CMAR or Construction Manager at Risk as he has implemented dozens of projects with his trusted approach, while always involving every stakeholder to ensure each individual receives the highest level of services expected.
Boulder City Acts Against Federal Approval of Townsite Solar II
NVBEX Staff
The Boulder City City Council has written an appeal letter after unanimously voting to act against the Townsite Solar II data center proposed on nearby federally owned land.
Townsite Solar II was initially proposed by Skyler Capital Management on an 88.5-acre site within Boulder City limits. After the Planning Commission recommended denial of the development, the developer withdrew the application and resubmitted it on federal land.
The Bureau of Land Management then granted its initial approval of the project without allowing public input, which is typically required per the National Environmental Policy Act. NVBEX has extensively covered this project.
Skylar Capital Management previously received approval to build a solar farm and then amended its permit to change the land use for a data center. BLM officials decided the environmental review that had already been conducted for the solar farm was sufficient for the data center.
The pivot to federal land means that any direct economic activity generated from the data center will not benefit Boulder City residents. (Source: Las Vegas Review-Journal)
We thought you may also like these articles...
Chosen Development Planning Four-Suite Warehouse Project in Clark County
Commercial Real Estate 05-19-26
Ulysses Development Group Planning Multifamily Complex in Clark County
Reno Multifamily Reaches New Equilibrium
Ken’s Foods Planning 421.3KSF Processing Center Expansion in Clark County
MTP Las Vegas Hangars Proposing Hangar Replacement Plan
Construction Employment Falls in March After Strong Start to 2026
Whiting Vegas Proposing Charter School in Sunrise Manor
Affordability Reform Legislation May Gut BTR Sector
Inland Group Proposing 204-Unit Senior Living Development in Carson City
Healthcare in Southern Nevada Shows Signs of Life, More Work Remains
Northern Nevada Industrial Market Continues to Chew Away at Recent Deliveries
Related Articles
NV Energy Planning $3B Worth of Capital Projects in Northern Nevada to Feed Data Centers
Reno Moves to Extend Data Center Moratorium Through August 2027
Boulder City Planning Commission Recommends Denial of 88.5-Acre Data Center Campus
LVGEA Announces $166M in Capital Investment
Proposed National Conservation Area Could Protect 185,000 Acres of Desert
Trending Now
336-Unit Townhome Community Planned in Reno
Nevada Projects 04-24-26
Boys & Girls Clubs of Mason Valley Planning New Campus in Silver Springs
Nevada Construction Employment Proceeds with 2026 Rebound
Commercial Real Estate 04-21-26