The Carson City Planning Commission voted to continue the Nevada Department of Administration Public Works Division’s proposed Office Complex during its Dec. 16 meeting.

The three-building Office Complex is estimated to cost $111M. The owner is the Nevada Department of Administration. TSK Architects is the architect. A general contractor is pending selection; proposals were due Nov. 4. The CMAR is tentatively scheduled to be selected on Feb. 10.

If fully approved, the complex is set to include two office buildings and a parking garage. The two office buildings will be 64.9KSF, respectively. The parking garage will be 155.8KSF. Collectively, this accounts for 285.6KSF of development. (NVBEX; Nov. 20; Dec. 17)

This marks the second consecutive continuance issued by the Planning Commission. The newest continuance pushes the hearing back to Feb. 25.

Representatives of the State and the City of Carson City both said this should be enough time to work out all the challenges.

As proposed, the three structures will be constructed on a 26-acre site zoned Public. The land is the former home of the Children’s Home. To make way for the proposed Office Complex, the vacant cottages were razed.

The Planning Commission raised concerns regarding parking lots along streets, as opposed to behind the buildings. Despite the concerns, the State opted not to change the plans.

Prior to the continuance, commissioners completed an annual review of the master plan. In this review, commissioners recommended a text correction that would affect State projects.

A staff report on the master plan review says, “In addressing the Capitol Complex and the State Office Complex, it states that these properties are not under the City’s jurisdiction. This is incorrect as per NRS 278.580, the State and its political subdivisions shall comply with all zoning regulations, except for the expansion of any activity existing on April 23, 1971.”

We thought you may also like these articles...
Carson City Considering Energy Restriction and 2027 Development Cap
Nevada Construction Employment Holds Steady in May 2026
UNLV Vegas Loop Station Returns to Board of Regents
Clark County Approves Switch Data Center Campus Expansion
Las Vegas Architects Discuss Upcoming Projects and AI Impact in Design

Leave a Reply

Your email address will not be published. Required fields are marked *

Learn More About Our Services

Mark Hobaica

Mark Hobaica

Executive Vice President

Core Construction

Since 2019, as CORE Construction’s Executive Vice President for Nevada, Mark ensures every client CORE serves receives the highest level of personalized care for every project. Mark’s passion is client Trust. He cares deeply about CORE’s reputation, partnerships and providing the highest quality and services, as well as most honest and best value possible. He has worked in the Las Vegas Valley and for the Public Works sector for nearly 35 years. He began as an owner in a local architectural firm designing and overseeing projects for Public Works clients for nearly 12 years. He clearly understands the expectations of the public sector, as he then directed numerous projects for over 16 years as the City Architect for the City of Henderson. His focus has always been delivering projects using CMAR or Construction Manager at Risk as he has implemented dozens of projects with his trusted approach, while always involving every stakeholder to ensure each individual receives the highest level of services expected.